Laying a Floor on a New Screed
Fitting guide 11 min read

Laying a Floor on a New Screed

How long a new screed takes to dry, the hygrometer reading that counts as dry, the flatness classes and the heating cycle, before any floor goes down.

Start reading

A new screed looks finished long before it is. It is flat, it is pale, it takes a footprint without marking, and it is still the wettest thing in the building. Most of the floors that fail in a new house fail because the covering went down on a screed that looked dry and was not, and the covering took the blame. This guide is about the three things a screed has to be before a floor goes on it: dry, flat and, where there is heating in it, commissioned.

On this page
  1. What the screed is
  2. How long it takes to dry
  3. How to know it is dry
  4. The membrane is not the test
  5. Flat enough for the floor
  6. Underfloor heating in the screed
  7. Letting the floor arrive
  8. Which floor, in a new house
  9. Common questions
  10. What the published standards say
  11. Who publishes this guide
01

What the screed is

Ask the builder for the screed's designation and you will get a short code. Under EN 13813 a screed material is named by its binder and its strength classes: CT is a cementitious screed and CA a calcium sulfate one, followed by C and the compressive strength class and F and the flexural strength class, so a common cement-based levelling screed is written EN 13813 CT-C12-F2. The code tells you what the screed is made of, and what it is made of decides how it dries and how it is tested, which is why it is worth having in writing before anyone quotes for the floor.

02

How long it takes to dry

BS 8204-1 gives a drying allowance for levelling screeds of one day per millimetre of thickness for the first 50 mm, with an increasing time for each millimetre above that. A 50 mm screed drying under good conditions can therefore be expected to be dry in about two months. Two things in that sentence do the damage on site. The first is "good conditions": a sealed new house with the windows shut and the heating off is not drying under good conditions, and the calendar says nothing about it. The second is the thickness: the allowance is not linear above 50 mm, so a thicker screed takes disproportionately longer, and the thickness is often not what the drawing says.

The drying allowance is a planning figure. It tells you when to start testing. It does not tell you the screed is dry.

03

How to know it is dry

The test in UK practice is a hygrometer sealed to the surface of the screed inside an insulated box with butyl tape, left until the air trapped under the box reaches equilibrium with the base, and then read. Where the damp-proof membrane sits between the base and a 50 mm screed, at least four hours pass before the first reading; where the membrane lies below the base slab, the wait is 72 hours. A reading taken sooner measures the air in the room, not the screed.

The figure that counts as dry: readings not exceeding 75 % relative humidity for most floor coverings, and 65 % for solid timber, as a hygrometer maker's data sheet that cites BS 8203, BS 5325 and BS 8201 puts it. The Contract Flooring Association's guide sets the same 75 % as the maximum before a floor finish goes down, alongside the other conditions it puts on the base: clean, sound, level, strong enough to carry the preparation and the finish, mechanically prepared and dust free. A floor laid on a screed that has not been read is a floor laid on an assumption.

04

The membrane is not the test

Approved Document C requires a floor next to the ground to resist the passage of ground moisture to its upper surface, not to be damaged by moisture from the ground or by groundwater, and to resist the passage of ground gases. A new ground floor therefore has a damp-proof membrane in it, and it is tempting to read that as permission to skip the hygrometer. It is not. The membrane deals with water coming up from the ground; the water in a new screed is the water it was mixed with, and it is above the membrane, drying upwards into the room. The test is about that water, and the membrane does nothing to it.

05

Flat enough for the floor

BS 8204 grades the surface regularity of a screed in three classes, measured as the greatest gap under a 2 m straightedge laid on the surface: SR1 allows 3 mm, SR2 5 mm and SR3 10 mm. Which class was specified is a question for the builder, and whether it was met is a question for a straightedge, not for the eye. What the class means for the floor depends on how the floor is fixed. A glued board follows the screed and shows every hollow as a hollow; a floating floor bridges the hollow, and a bridged hollow becomes a soft spot under a click joint. Either way the answer to a screed outside its class is a levelling compound before the floor, not a thicker underlay.

06

Underfloor heating in the screed

Where the heating pipes are in the screed, the Contract Flooring Association is unambiguous: the system must be run through a full drying and commissioning cycle of heating up and cooling down before any subfloor preparation or floor covering goes down, and that cycle usually takes around 21 days. The guidance calls it a drying and commissioning cycle, and the order of the two words matters: the screed is taken through its working temperatures while there is still nothing on top of it to take the consequences. A heated screed that has not been through the cycle is not ready, whatever the hygrometer says on the day.

07

Letting the floor arrive

The last condition is the room, not the screed. The CFA's guide says the room should be at its in-service temperature 48 hours before installation, so that the flooring can be kept in the room and brought to room temperature before it is laid. For multilayer modular floors, rigid vinyl among them, the MMFA puts the same 48 hours on the boards themselves: stored flat and cross-stacked in their unopened boxes, in the same conditions as the installation area, at roughly 15 to 25 °C and between 35 and 65 % relative humidity. A pallet that came off a cold van the same morning has not met either condition.

08

Which floor, in a new house

Once the screed is dry and flat, the choice is the usual one. The BML rigid vinyl in the range arrives with its underlay backing attached and clicks together as a floating floor. Laminate floats over a separate underlay, and on a screed that underlay carries a moisture barrier. Engineered oak can float over an underlay with a barrier or be bonded to the screed; solid oak is fixed, and it is the covering the stricter 65 % figure was written for. None of them changes the order of events: read the screed, level it, run the heating, let the boards settle, then lay.

See also
09

Common questions

How long does a new screed take to dry?

The allowance in BS 8204-1 is one day per millimetre for the first 50 mm of a levelling screed and longer per millimetre above that, so a 50 mm screed in good conditions takes about two months. Treat it as the date to start testing rather than the date the floor can go down, because a closed, unheated house is not good conditions.

What hygrometer reading counts as dry?

Readings not exceeding 75 % relative humidity for resilient floor coverings, and 65 % for solid timber, with the hygrometer sealed to the screed in an insulated box and left long enough to reach equilibrium: at least four hours on a 50 mm screed with the membrane beneath it, and 72 hours where the membrane is below the base slab.

The builder says there is a damp-proof membrane. Do I still need the test?

Yes. The membrane satisfies the requirement in Approved Document C that a ground floor resists moisture from the ground. The water in a new screed is the mixing water above the membrane, and only a hygrometer reading tells you whether it has gone.

Do I have to run the underfloor heating before the floor is laid?

Yes, where the heating is in the screed. The Contract Flooring Association requires a full heating-up and cooling-down commissioning cycle before any subfloor preparation or floor covering, and says it usually takes around 21 days.

New-build estates have a different floor beneath the floor from the terraces and semis around them, and the towns we deliver to have both. Browse by town and region.

See also
10

What the published standards say

Each entry is quoted from its source and linked to it. The full set is in the standards reference.

1 of 10
Ronacrete

How long a screed takes to dry

1 day per mm drying allowance, first 50 mm
50 mm thickness covered by the 1 day/mm rule
about 2 months resulting drying time for a 50 mm screed, good conditions

BS 8204-1 gives a drying allowance of one day per millimetre of thickness for the first 50 mm of a levelling screed, with longer per-millimetre times above that thickness, so a 50 mm screed drying in good conditions takes roughly two months.

The exact wording

“with levelling screeds, one day should be allowed for each millimetre of thickness for the first 50 mm, followed by an increasing time for each millimetre above this thickness. It is therefore reasonable to expect a levelling screed 50 mm thick, drying under good conditions, to be sufficiently dry in about 2 months.”

Source: Drying of Screeds - Ronacrete
F. Ball and Co.

BS 8203 — relative humidity limit for a subfloor

75 % RH RH limit, resilient floor coverings
65 % RH RH limit, solid timber floor coverings

A hygrometer maker's data sheet that cites BS 8203, BS 5325 and BS 8201 treats a subfloor as dry enough for most floor coverings when hygrometer readings do not exceed 75% relative humidity (65% RH for solid timber coverings), measured with a hygrometer sealed to the surface so that it reaches equilibrium with the base.

The exact wording

“The base can be considered dry enough to install most floorcoverings if a series of tests produce readings not exceeding 75% R.H. (65% R.H. for solid timber floorcoverings).”

Source: F. Ball and Co. Ltd - Digital Hygrometer, Technical Data Sheet
F. Ball and Co.

The hygrometer method for subfloor moisture

4 hours minimum time before first reading, 50 mm screed with DPM between base and screed
72 hours minimum time before first reading, DPM below the base slab

In UK practice a hygrometer is sealed to the subfloor inside an insulated box with butyl tape and left until the air under the box reaches equilibrium; at least 4 hours before the first reading on a 50 mm screed with the DPM under the screed, and 72 hours where the DPM lies below the base slab.

The exact wording

“For 50mm thick screeds, where the damp proof membrane is placed between the base and the screed, a period of at least 4 hours should be allowed before the first reading is taken. For thicker constructions i.e. where the damp proof membrane is placed below the base slab, a period of 72 hours should be allowed to elapse before the first reading.”

Source: Digital Hygrometer - Technical Data Sheet, F. Ball and Co. Ltd
Tarmac

BS EN 13813 — how a screed is designated

CT cementitious screed binder code
CA calcium sulfate screed binder code
C compressive strength class prefix
F flexural strength class prefix
EN 13813 CT-C12-F2 example designation, cementitious
EN 13813 CA-C12-F3 example designation, calcium sulfate

EN 13813 designates a screed material by its binder abbreviation followed by strength classes: CT for cementitious and CA for calcium sulfate screed, then C plus the compressive strength class and F plus the flexural strength class.

The exact wording

“A cementitious screed material (CT) not used as a wearing surface in compressive strength class C12 and flexural strength class F2 is designated by: EN 13813 CT-C12-F2”

Source: Data Sheet No. 18 Introduction - screed materials to EN 13813 (Tarmac)
UK Government

Damp-proof membrane — Approved Document C

4.2 paragraph in Approved Document C
C2 Resistance to moisture requirement covered

Approved Document C, paragraph 4.2, states that floors next to the ground should resist the passage of ground moisture to the upper surface, not be damaged by moisture from the ground or by groundwater, and resist the passage of ground gases.

The exact wording

“Floors next to the ground should: a. resist the passage of ground moisture to the upper surface of the floor; b. not be damaged by moisture from the ground; c. not be damaged by groundwater; d. resist the passage of ground gases.”

Source: Approved Document C - Site preparation and resistance to contaminants and moisture, 2013 edition (HM Government)
Contract Flooring Association

CFA guidance — the subfloor is the installer’s first responsibility

75 % RH maximum hygrometer reading before laying a floor finish

The CFA Guide to Contract Flooring requires the base to be a clean, sound, level surface that is strong enough to carry the preparation materials and the floor finish, mechanically prepared and dust free, and dry enough to give a hygrometer reading of no more than 75% relative humidity.

The exact wording

“Before the application of the floor finish a solid (cementitious or similar) base must be sufficiently dry to show a hygrometer reading not greater than 75% Relative Humidity when tested in accordance with the British Standard Code of Practice.”

Source: CFA Guide to Contract Flooring - Contract Flooring Association
The Concrete Society

BS 8204 — surface regularity classes SR1 to SR3

3 mm SR1 (max deviation under 2 m straightedge)
5 mm SR2 (max deviation under 2 m straightedge)
10 mm SR3 (max deviation under 2 m straightedge)
2 m straightedge length

BS 8204 defines three surface regularity classes for screeds and concrete bases, SR1, SR2 and SR3, measured as the maximum deviation below a 2 m straightedge placed directly on the surface.

The exact wording

“Surface regularity classes are given in BS 8204 as SR1, SR2 and SR3 relating to 3mm, 5mm and 10mm respectively.”

Source: Surface regularity - straightedge method | The Concrete Society
Contract Flooring Association

Commissioning the heating before the floor goes down

21 days typical duration of the heat-up / cool-down commissioning cycle

Before any subfloor preparation or floorcovering is laid, the underfloor heating must be run through a full drying and commissioning cycle of heating up and cooling down, typically lasting about 21 days.

The exact wording

“In all instances, UFH systems must be run through a full drying / commissioning cycle of heating up and cooling down before any subfloor preparation or installation of decorative floor coverings are installed. This period of commissioning is usually around 21 days.”

Source: CFA Guidance Document — Beyond Installation: Guidance on Underfloor Heating (Contract Flooring Association)
Contract Flooring Association

Acclimatisation before fitting

48 h conditioning before installation

The Contract Flooring Association's guide asks for a steady room temperature of 18 to 27 °C, reached 48 hours before installation, so that the flooring can be kept in the room and reach room temperature before it is laid.

The exact wording

“They also advise that this temperature should be attained 48 hours prior to the installation, so that floorings can be kept in the room and brought to room temperature (acclimatised) before installation.”

Source: CFA Guide to Contract Flooring - Contract Flooring Association
Multilayer Modular Flooring Association

Room conditions at the time of fitting

at least 48 h acclimatisation before installation
15-25 °C storage and acclimatisation temperature
35-65 % storage and acclimatisation relative humidity

The MMFA, the European association for multilayer modular floor coverings, requires the flooring to acclimatise for at least 48 hours in the same conditions as the installation area, stored flat and cross-stacked in unopened boxes at roughly 15-25 degrees Celsius and 35 to 65 per cent relative humidity.

The exact wording

“Leave the floor covering to acclimatise in the same environmental conditions as the installation area for a period of at least 48 hours prior to installation. Always store the boards flat and cross-stacked, in their original unopened boxes and at approx. 15-25 °C and between 35 % and maximum 65 % relative humidity.”

Source: Prior to installation — MMFA (Multilayer Modular Flooring Association)
11

Who publishes this guide

Homes and Floors Ltd, registered in England and Wales, company number 11762665, incorporated in January 2019. Endeavour House, Floor 3, Coopers End Road, Stansted CM24 1SJ.

Where a guide quotes a standard or a regulation, the source is named and linked. Product figures come from the specifications on the product pages. If something here is wrong, tell us at info@homesandfloors.com and we will check it.

First published . Last updated .

Your next step
Fitting it yourself, or having it fitted?
Either way, the board in your hand answers questions a datasheet cannot. Samples first, then the fitter.
  • Samples £1.99 each
  • UK-wide delivery
  • Advice before you order

Join the Homes & Floors Club

New ranges and offers. Hear it first.

  • Room ideas & honest guides
  • New floors first
  • Special offers

No spam. Unsubscribe any time.