Commissioning Underfloor Heating Before the Floor Goes Down
Underfloor heating 4 min read

Commissioning Underfloor Heating Before the Floor Goes Down

When the screed can first be heated, the functional heating programme, the 21-day commissioning cycle, and why a heated screed is not yet a dry one.

Guide type
Underfloor heating
Reading time
4 min
First reading, 50 mm screed
4 hours
RH limit, resilient floors
75 % RH

A floor laid over underfloor heating that has never been run is a floor laid before the building is finished. The heating has to be taken through its working temperatures with nothing on top of it, the screed it sits in has to be dry, and those are not the same thing. This guide sets out the order of events, with the published figures for each step.

1/ 8
01

Step one: let the screed cure

A heated screed is not heated straight away. IMI, a maker of underfloor heating components, gives the earliest start for functional heating in its commissioning instructions, which follow EN 1264-4: 21 days after laying for a cement screed, 7 days for an anhydrite one. The screed manufacturer's own information comes first where it differs.

02

Step two: functional heating

The same instructions set the programme: begin at a flow temperature of 20 to 25 °C and hold it for 3 days, then set the maximum design temperature and hold it for 4 days. Functional heating proves the system and takes the screed through the temperatures it will see in use, while there is still nothing on top of it to suffer for it.

The Contract Flooring Association describes the same principle from the floor layer's side: in all instances the heating must be run through a full drying and commissioning cycle of heating up and cooling down before any subfloor preparation or floor covering, and that period is usually around 21 days. The heating engineer and the floor layer should agree in advance whose programme is being run and when it ends.

03

Step three: measure, do not assume

Heating a screed is not the same as drying it. IMI says so directly: functional heating does not ensure that the screed has reached the moisture content needed before it can be covered, and that readiness is checked by the floor layer. The check in UK practice is a hygrometer sealed to the screed in an insulated box and left to reach equilibrium: at least 4 hours on a 50 mm screed with the membrane beneath it, 72 hours where the membrane is below the base slab. Readings not exceeding 75 % relative humidity count as dry for resilient floor coverings such as vinyl, and 65 % for solid timber.

How long the screed takes to get there is a separate figure. BS 8204-1 allows one day per millimetre for the first 50 mm of a levelling screed and longer per millimetre above that, so a 50 mm screed in good conditions takes about two months. A date on the calendar says when to start testing, not that the test will pass.

See also
04

Step four: the floor arrives before it is laid

The Contract Flooring Association asks for the room to be at its in-service temperature 48 hours before installation, so that the flooring can be kept in the room and reach room temperature before it is laid. For multilayer floors such as rigid vinyl, the MMFA asks for at least 48 hours in the same conditions as the installation area, at roughly 15 to 25 °C and 35 to 65 % relative humidity. What the heating itself should be doing on the day of fitting is set by the instructions for the floor, and they are worth reading before the fitter arrives.

05

Step five: the floor's limits take over

Once the floor is down, the heating works to the floor's limits rather than the screed's. BEAMA notes that most floor covering manufacturers state a maximum surface temperature of 27 °C and that most vinyls should not be heated above 26 °C. For parquet it advises a floor temperature sensor always fitted, and for any floor a sensor wired to the thermostat is what keeps the surface where the instructions say.

See also
06

Common questions

How long after screeding can underfloor heating be switched on?

IMI's commissioning instructions, following EN 1264-4, give the earliest start for functional heating as 21 days after laying for a cement screed and 7 days for an anhydrite screed. The screed manufacturer's information comes first where it differs.

How long does commissioning take?

IMI's functional heating programme is 3 days at a flow temperature of 20 to 25 °C followed by 4 days at the maximum design temperature. The Contract Flooring Association puts the full heating-up and cooling-down cycle before any floor covering at usually around 21 days.

Does running the heating dry the screed enough to lay the floor?

No. IMI states that functional heating does not ensure the screed has reached the moisture content needed for covering. A sealed hygrometer reading not exceeding 75 % relative humidity, or 65 % for solid timber, is the test.

Who decides that the screed is ready for the floor?

The floor layer, on a measurement. IMI's instructions say the readiness for covering is checked by the floor layer, and in UK practice that check is a hygrometer sealed to the screed.

What temperature should the heating run at once the floor is down?

The figure in the floor's instructions. BEAMA notes that most floor covering manufacturers state 27 °C at the surface and that most vinyls should not go above 26 °C.

New builds with underfloor heating are on every delivery route we run. Browse by town and region.

See also
07

What the published standards say

Each entry is quoted from its source and linked to it. The full set is in the standards reference.

Functional heating of a heated screed

IMI's commissioning instructions start functional heating of a heated screed no earlier than 21 days after laying for cement screed and 7 days for anhydrite, at 20 to 25 °C flow temperature for 3 days and then at the maximum design temperature for 4 days, in keeping with EN 1264-4, and state that functional heating does not ensure the screed is dry enough to be covered; that readiness is checked by the floor layer.

earliest start, cement screed21 days
earliest start, anhydrite screed7 days
first stage flow temperature20-25 °C
first stage duration3 days
second stage at maximum design temperature4 days

“Carry out functional heating of heating screed conforming to standards in keeping with EN 1264-4. Earliest start for functional heating: – Cement screed: 21 days after laying – Anhydrite screed 7 days after laying Begin 20 °C - 25 °C flow temperature and maintain for 3 days. Then set maximum design temperature and maintain for 4 days. … Functional heating does not ensure that the screed has reached moisture content for readiness for covering. The readiness for covering the floor will be checked by the floor layer.”

Source: IMI Hydronic Engineering — Commissioning instructions for underfloor heating (9340-00.831-480, Index 00, 04.2021)

Commissioning the heating before the floor goes down

Before any subfloor preparation or floorcovering is laid, the underfloor heating must be run through a full drying and commissioning cycle of heating up and cooling down, typically lasting about 21 days.

typical duration of the heat-up / cool-down commissioning cycle21 days

“In all instances, UFH systems must be run through a full drying / commissioning cycle of heating up and cooling down before any subfloor preparation or installation of decorative floor coverings are installed. This period of commissioning is usually around 21 days.”

Source: CFA Guidance Document — Beyond Installation: Guidance on Underfloor Heating (Contract Flooring Association)

The hygrometer method for subfloor moisture

In UK practice a hygrometer is sealed to the subfloor inside an insulated box with butyl tape and left until the air under the box reaches equilibrium; at least 4 hours before the first reading on a 50 mm screed with the DPM under the screed, and 72 hours where the DPM lies below the base slab.

minimum time before first reading, 50 mm screed with DPM between base and screed4 hours
minimum time before first reading, DPM below the base slab72 hours

“For 50mm thick screeds, where the damp proof membrane is placed between the base and the screed, a period of at least 4 hours should be allowed before the first reading is taken. For thicker constructions i.e. where the damp proof membrane is placed below the base slab, a period of 72 hours should be allowed to elapse before the first reading.”

Source: Digital Hygrometer - Technical Data Sheet, F. Ball and Co. Ltd

BS 8203 — relative humidity limit for a subfloor

UK practice following BS 8203 treats a subfloor as dry enough for resilient floor coverings when hygrometer readings do not exceed 75% relative humidity (65% RH for solid timber coverings), measured with a hygrometer sealed to the surface so that it reaches equilibrium with the base.

RH limit, resilient floor coverings75 % RH
RH limit, solid timber floor coverings65 % RH

“The base can be considered dry enough to install most floorcoverings if a series of tests produce readings not exceeding 75% R.H. (65% R.H. for solid timber floorcoverings).”

Source: F. Ball and Co. Ltd - Digital Hygrometer, Technical Data Sheet

How long a screed takes to dry

BS 8204-1 gives a drying allowance of one day per millimetre of thickness for the first 50 mm of a levelling screed, with longer per-millimetre times above that thickness, so a 50 mm screed drying in good conditions takes roughly two months.

drying allowance, first 50 mm1 day per mm
thickness covered by the 1 day/mm rule50 mm
resulting drying time for a 50 mm screed, good conditionsabout 2 months

“with levelling screeds, one day should be allowed for each millimetre of thickness for the first 50 mm, followed by an increasing time for each millimetre above this thickness. It is therefore reasonable to expect a levelling screed 50 mm thick, drying under good conditions, to be sufficiently dry in about 2 months.”

Source: Drying of Screeds - Ronacrete

Acclimatisation before fitting

The Contract Flooring Association's guide states that the room should be at its in-service temperature 48 hours before installation so that the flooring can be kept in the room and reach room temperature before it is laid.

conditioning before installation48 h

“They also advise that this temperature should be attained 48 hours prior to the installation, so that floorings can be kept in the room and brought to room temperature (acclimatised) before installation.”

Source: CFA Guide to Contract Flooring - Contract Flooring Association

Room conditions at the time of fitting

The MMFA, the European association for multilayer modular floor coverings, requires the flooring to acclimatise for at least 48 hours in the same conditions as the installation area, stored flat and cross-stacked in unopened boxes at roughly 15-25 degrees Celsius and 35 to 65 per cent relative humidity.

acclimatisation before installationat least 48 h
storage and acclimatisation temperature15-25 °C
storage and acclimatisation relative humidity35-65 %

“Leave the floor covering to acclimatise in the same environmental conditions as the installation area for a period of at least 48 hours prior to installation. Always store the boards flat and cross-stacked, in their original unopened boxes and at approx. 15-25 °C and between 35 % and maximum 65 % relative humidity.”

Source: Prior to installation — MMFA (Multilayer Modular Flooring Association)

Floor surface temperature: what most manufacturers state

The UK underfloor heating trade association says most floor covering manufacturers state a maximum floor surface temperature of 27 °C, which is more than adequate in the majority of situations, and that some manufacturers allow higher temperatures without compromising warranties.

maximum floor surface temperature stated by most manufacturers27 °C

“Most manufacturers state 27°C, which is more than adequate in the majority of situations. In some circumstances, manufacturers will allow higher temperatures without compromising warranties.”

Source: BEAMA Underfloor Heating — Choosing your floor covering to maximise your underfloor heating efficiency (April 2020)

Vinyl over underfloor heating: 26 °C

BEAMA advises that most vinyls should not be heated above 26 °C, so the floor temperature should be restricted, and warns that in rooms with high heat losses such as conservatories a restricted floor temperature may not heat the room sufficiently.

maximum temperature for most vinyls26 °C

“However, as most vinyls should not be heated to above 26°C, the floor temperature should be restricted. Care should be taken in the design of systems in rooms with high heat losses, such as conservatories, as it may not be possible to sufficiently heat the room with a restricted floor temperature limit.”

Source: BEAMA Underfloor Heating — Choosing your floor covering to maximise your underfloor heating efficiency (April 2020)

Parquet over underfloor heating: glued down, with a floor sensor

BEAMA describes parquet as suitable for underfloor heating, with the blocks continuously glued onto the screed or timber deck for good heat transfer and a floor temperature sensor always fitted.

“Parquet – Also suitable for use with underfloor heating, these floor blocks should be continuously glued onto the screed or timber deck for good heat transfer. A floor temperature sensor should always be fitted.”

Source: BEAMA Underfloor Heating — Choosing your floor covering to maximise your underfloor heating efficiency (April 2020)
08

Who publishes this guide

Homes and Floors Ltd, registered in England and Wales, company number 11762665, incorporated in January 2019. Endeavour House, Floor 3, Coopers End Road, Stansted CM24 1SJ.

Where a guide quotes a standard or a regulation, the source is named and linked. Product figures come from the specifications on the product pages. If something here is wrong, tell us at info@homesandfloors.com and we will check it.

First published .

Still deciding?
A sample on the floor, in the room it is for, answers most of what a description cannot.
Newsletter

New ranges and offers. Hear it first.

Unsubscribe anytime